Is anybody aware of the change in the "Estimated Completion Date" of prosensa clinical trial?

The comletion date was August 2012, but they changed it to July 2013 in 27.07.2012.

http://www.clinicaltrials.gov/ct2/show/NCT01254019?term=GSK+and+Duc...

Why did they changed the date?

Thanks.

Views: 320

Reply to This

Replies to This Discussion

Dietf,

They just finished recruiting this August 2012, and now those latest boys have one year of drug injections before their results will be ready. The link below states "end of 2013".

https://www.duchenneconnect.org/index.php?option=com_content&vi...

A.

I think you maybe confusing, Pro 51 phase III study "Estimated Completion Date" July 2013

with

Pro 44 phase I/IIA study "Estimated Completion Date" of August 2012

Thank you all for the information.